Proposed Schedule (June 2001 Flight)
June,2000 Fab ACD, CAL, TKR Interface boards for BFEM (done)
July, 2000 Balloon Flight Requirements Review
July, 2000 TKR Testing at UCSC
Aug 1, 2000 Requirements Document Draft
Aug, 2000 ACD Interface Test
Oct 1, 2000 Balloon Flight Review: Final Requirements, Draft Design
Oct, 2000 CAL Interface Test
Oct, 2000 Power System, HSK Board, and Pressure Vessel Fab
Nov, 2000 BIU Interface Test at NRL
Jan 8, 2001 All detectors at Stanford
Jan 8-12, 2001 Hardware Integration
Jan 15-19, 2001 Hardware/Detector Team Testing
Jan 22-Feb 16 Software Integration and Testing
Feb 19-23 1 week pack and ship to GSFC
Feb 26 - Mar 9 2 week Gondola Assembly and Test
Mar 12 -Apr 6 4 week Software Integration and Test
Apr 9 - 13 Pack and Ship to Launch Site
Apr 16-27 Flight Preparations